Read the email below and answer the questions.

再生ボタンを押すと本文の音声が流れます。Part7にリスニングはありませんが、シャドーイングなどにご活用ください。

No.1. What has the construction team recently completed?




No.2. What is the project’s current status?





解答

001の答え

001. 建設チームは最近何を完成させましたか?
A: 室内の装飾
B: 基礎工事
C: 外壁
D: リスク評価報告書
正解 B: The foundation work

002の答え

002. プロジェクトの現在の状況は何ですか?
A: 予定より遅れている
B: 承認待ち
C: 予定通り
D: 完成した
正解 C: On schedule

英文

Dear Project Stakeholders,

I am writing to provide a quick update on the progress of the Riverside Plaza construction project. As of this week, we have completed the foundation work and the framing of the lower levels is underway. The project remains on schedule and we are actively managing risks to ensure continued progress.

The recent mild weather has been favorable and has allowed our teams to advance more rapidly than anticipated. We expect to begin external work on the facade by next month, pending any unforeseen delays.

Thank you for your continued support.

Best regards,
Alex Reed
Project Manager

和訳

プロジェクト関係者の皆様へ、

リバーサイドプラザ建設プロジェクトの進捗状況を簡単にお知らせいたします。今週現在、基礎工事が完了し、下層の骨組み作業に取り掛かっています。プロジェクトは予定通り進行しており、進捗を確宜するためリスクを積極的に管理しています。

最近の穏やかな天気が好条件となり、予想よりも迅速に作業を進めることができました。来月には外壁工事に取り掛かる予定ですが、予期せぬ遅延がない限りです。

引き続きのご支援をありがとうございます。

敬具,
アレックス・リード
プロジェクトマネージャー